During the rescue period, the machine and
personnel of our heavy machinery team were brought into Shui Li, Cao Tun,
Guo Shin Hsiang in Nan Tou and responsible to cleave roads, dismantle dangerous
houses, rescue buried people, environmental sanitary, water supply and bridge
repair, etc. In order to operate the rescue mission, the machinery team sent in total the following personnel and machines. 1. Rescue personnel: 699 people/times 2. Excavator: 142 sets/times 3. Truck: 162 sets/times 4. Loader: 8 sets/times 5. Bulldozer: 6 sets/times 6. Water Truck: 134 sets/times |
7. Large-sized generator: 12 sets/times (To
illuminate and refrigerate corpses) 8. Car and trailer: 219 sets/times |
|
¡@ |
Construction and planning Administration
of Ministry of Interior
|